Desal Startup Delayed Again

Operations Now Scheduled to Begin Mid-March

Wed Nov 23, 2016 | 12:00am
Santa Barbara's dormant water desalination plant.
Paul Wellman

The start-up date for Santa Barbara’s desalination plant has been pushed back again, this time to mid-March 2017. City water czar Joshua Haggmark notified the Water Commission of the latest delay at a meeting last week, prompting Commissioner Barry Keller to comment afterward, “Things have gone from worse to Worcestershire.”

According to Haggmark, construction crews recently connected two stretches of underwater pipeline, which he termed a “major milestone” and something “we were nervous about.” Haggmark also said the desal plant has been successfully hooked up to the power grid and should begin receiving actual seawater sometime in mid-December. After pumping starts, a 40-day “maturation” process is required, during which time the media of the water filtration membranes are biologically cured. Haggmark stressed that the engineering and construction process is highly complex, adding, “There’s still a lot of vulnerability out there.”

Haggmark said some of the delays so far stemmed from unanticipated issues, such as lead contamination in the soil surrounding the onshore facility. Others he described as being “unexcused,” but he said he’s been assured by the contractor that the project will be successfully completed. The $60 million question, of course, is when. “If it’s anytime in February, I’ll be happy,” said Keller.

Continue reading

Subscribe for Exclusive Content, Full Video Access, Premium Events, and More!

Subscribe

More like this

Exit mobile version