The work to remove the pier and caisson structures, known as PRC 421-1 and 421-2, at Haskell’s Beach is going well and is on schedule to be completed by early next year. At the end of August, the State Lands Commission in collaboration with the City of Goleta began the work which will up to six months to complete. Sections of the beach may close temporarily to keep the public safe during the operations, but the beach will remain open otherwise.

The State Lands Commission is currently in the process of dismantling the first Pier (421-1), and removal is expected in mid-November. Removal work on the second Pier (421-2), is expected to start in mid-December.

Crews are working Monday through Friday from 6:00 a.m. to 5:00 p.m. Due to the surf zone location of the facilities, some work must be scheduled around low-tide cycles, which may be outside of these hours. The project requires the use of heavy equipment at the worksite and the transport of approximately 500 truckloads of material to an approved recycling and disposal facility. Crews will access the worksite via the existing gravel access road adjacent to the Ellwood Onshore Facility and along a 12’-wide easement across the Sandpiper golf course and along the cliff to the piers. Removal of the piers and caissons will require equipment access along the beach during low tides.

The Commission prepared an Environmental Impact Report and secured permits for this project in collaboration with federal, state, and local agencies. More information can be found at: www.slc.ca.gov/ceqa/prc-421-decommissioning-project.

Most Popular Photos/Videos

Login

Please note this login is to submit events or press releases. Use this page here to login for your Independent subscription

Not a member? Sign up here.